Construction Updates and Notices

Project Summaries

Below is a list of the major active construction projects in the City that have an impact on daily traffic. Projects are listed below, by the primary street that is impacted. To find out more details regarding work on a specific street, including construction schedules, select the street name and the field will expand to show additional information.

Please note that the completion dates listed below are approximate dates, based on schedules provided to the City by the contractors/developers for each project. Unexpected field conditions, inclement weather, and other unforeseen circumstances may impact schedules.

Please check this site for regular updates.

For questions, please email the Public Works/Engineering Department at [email protected],
or call 951-677-7751 x5.


City Construction Projects

Bundy Canyon Rd.

Palomar St.

  • Project: Palomar St./Clinton Keith Rd. Sidewalk, Trail, and Bike Lane Connectivity Project
  • Project No.: CIP 059
  • Project Type: City Capital Improvement Project
  • Project Description:
    • Construction of new sidewalks, trails, bike lanes, and roadway widening.
    • Note: Full road closures are not anticipated, but various temporary lane closures may occur. Drivers should anticipate delays during working hours (7:00 am - 3:30 pm).
  • Roadway Segments:
    • Palomar St. from Meadowridge Ln. to Clinton Keith Rd.
    • Clinton Keith Rd. (south side) adjacent to Stable Lanes Rd.
  • Project Schedule:
    • Expected Start: July 2022
    • Expected End: January 2023
    • Note: Construction schedules are subject to change for various reasons including but not limited to weather conditions, unforeseen emergencies, other acts of nature, and other unforeseen conditions.
  • Project Map:

Project Map

 
Developer Construction Projects

Please note that the completion dates listed below are approximate dates, based on schedules provided to the City by the contractors/developers for each project. Unexpected field conditions, inclement weather, and other unforeseen circumstances may impact schedules.
 
 

Lennar Homes - Horizons

 Horizons Map

Update (9/30/22):

  • Prielipp construction is still underway.  Base paving and compaction are complete.  Procurement of AC and concrete has delayed completion again, due to supply chain issues. We sincerely apologize for the inconvenience, and are working onsite with the developer and their contractor to assist however we can so the construction can be completed as quickly as possible, and the road reopened to through traffic.


Please see 'Overall Project Schedule' below for additional details.


Update (9/22/22):

  • Prielipp construction is underway.  Completion still expected the week of 9/30, pending no additional field issues.

Update (9/15/2022):

  • Headwall for storm drain facilities currently under construction.
  • Prielipp widening and improvements expected to begin in the next few weeks.

Update (9/7/2022):

  • No new updates.

Update (8/31/2022):

  • Contractor will be working on fire hydrant tie-ins.
  • Curb and gutter staking for Prielipp and Elizabeth will be installed.
  • Construction of curb and gutter will be followed by street improvements.

Update (8/25/22)

  • No new updates.  Project schedule updated on 8/17/22 is still current.

Update (8/17/22)

  • All storm drain in Prielipp Road has been constructed.
  • Relocation of fire hydrants along Prielipp is underway.
  • Domestic water construction in Elizabeth Lane is underway.
  • Wet utilities at the Prielipp and Elizabeth Lane intersection are complete.
  • Headwall/retaining wall for drainage outlet structure along Prielipp is scheduled for construction within the next two weeks.
  • After completion of headwall/retaining wall, paving/widening on Prielipp can commence.

Update (7/22/22):

  • All in-tract sewer proposed completion early next week.
  • Water line construction set to begin next week. 
  • Dry utility construction will begin at the end of August. 
  • In-tract curb and gutter construction will begin next week.
  • Contractor will begin recertifying all pads due to erosion.  


Overall Project Schedule (Updated on 9/30/22):




Beazer Homes, Boulder Creek 

Beazer Map

Update (9/15/2022):

  • Partial re-opening of McVicar Street from Whispering Way to Grand Avenue
  • Curb and Gutter on Grand is 50% complete.
  • No updates on the project schedule.
Please see 'Overall Project Schedule' below for additional details.

Update (9/7/2022):

  • Off Tract Improvements
    1. Grand Avenue – pouring curb and gutter
    2. McVicar Street from Grand Avenue to Whispering Way – street improvement work
  • No updates on the project schedule.

Update (9/1/2022):

  • No new updates.  Project Schedule below has been updated.

Update (8/24/2022):

  • Edison de-energizing facilities at culvert:  a portion has been de-energize, waiting for a portion with street light facilities and facilities running under culvert. ETA for this is 9/30/22.
  • The goal is to have McVicar 100% open and paved completely over culvert by 2/28/23.

Update (8/17/22):

  • Construction of storm drain connections at the intersection of Grand and McVicar is in progress and should be completed by the end of the week.
  • McVicar utilities are complete, with the exception of the RCFC box culvert (master planned facilities), and is now base paved with curb and gutter almost complete.
  • Curb and gutter is being constructed on Grand, and relocation of SCE poles will soon follow.

Update (7/22/22):

  • Working on Storm Drain in McVicar in coordination with RCFC in field.  Projected start of construction for box culvert, at the end of August. 
  • BMPs, graffiti, and traffic control was in disarray – everything has been cleaned up as of today.
  • Traffic Control on McVicar has been updated per City Traffic Engineer’s request.

 
Overall Project Schedule (Updated 9/1/22): 







Baxter Village

BV

Update (9/15/2022):

  • Installation of utility laterals across Wildomar Trail.
 Please see 'Overall Project Schedule' below for additional details.

Update (8/31, 9/1/2022):

  • No updates at this time. 

Update (8/25/22):

  • First phase of new road paving is projected to begin on 9/13/22.
  • First phase of Wildomar road crossing of wet utilities to be completed by 8/26/22.
  • Contractor might need a day or two of lane closures during the week of 9/6 for dry utilities (landscape sleeves, traffic, street light conduits and communication cables.
  • Contractor will be making lane changes the week of 9/13 during paving operations per traffic control plans.

Update (8/17/22):

  • Water and storm drain line construction with traffic crossing Wildomar Trail scheduled for 8/18 through 8/30.
  • First section of paving on Wildomar Trail is scheduled to begin on or around 9/13/22.

Update (7/22/22):

  • Sewer and water line work across Wildomar Trail will begin next Tuesday-7/26-Wednesday, 7/27 during the hours of 9:00 am-2:00 pm.  Sewer will begin first.
  • Road depression at project truck crossing will be fixed at the same time. 
  • All work will utilize the existing lane closure with flagmen & traffic control.
  • Traffic plates will be anchored and welded for safety and will remain in place until the new road witches over.
  • Waterline construction is scheduled to commence after sewer is complete.


Overall Project Schedule (No change from 8/18/22):
Schedule


 

 
 


KB Homes - Verano

KB Map

Update (9/15/2022):

  • No new updates.  

Please see 'Overall Project Schedule' below for additional details.

Update (9/7/2022):

  • No new updates.  

Update (8/31/2022):

  • No new updates.  Project Schedule below has been updated.

Update (8/24/2022):

  • No new updates.  Project Schedule below has been updated with completed work.

Update (8/17/22):

  • Construction of shoulder improvements on Summer Sage Way are nearing completion.
  • In-tract sewer, water, and storm drain are currently under construction.

Overall Project Schedule (Updated on 8/31/22):

 

IVMC Expansion Project

IVMC

Update (9/15/2022):

  • No new updates.  

Please see 'Overall Project Schedule' below for additional details.

Update (8/29/22):

  • The temporary parking lot at Yamas and Prielipp will no have any road closures associated with the work.
  • 2nd approach was poured on 8/24/22 since material was released early.
  • Site work was scheduled to be completed Friday 8/25 and the project will be turned over for use.

Update (8/18/22):

  • DPR Construction-directed work is all occurring on-site at the Inland Valley Medical Center campus.
  • Ongoing activities are mainly grading activities, with various underground utility work ongoing and some of the temporary infrastructure work for the buildings (under HCAI permits).
  • It has been reported that the temporary parking lot at Prielipp and Yamas is scheduled for completion by the end of August.

Overall Project Schedule: